Semester
Project The semester project will involve a comprehensive modification of Gould
Hall for the College of Architecture. The intent, through additions and rehabilitation
is to provide space for all five divisions in one building. Semester Schedule:
Phase One: Data Collection (20%) Students in Section 001 and 002 will be assembled
into four teams for Phase One work as outlined below.
1. Program
This
team will be responsible for development of a comprehensive program for the College
of Architecture to be housed entirely in Gould Hall. Interviews must be conducted
with the OU Vice President for Information Technology, Campus Architect, Dean
Fillpot, Division Directors and other appropriate individuals. Program materials
must be assembled into a coherent document, identifying all spaces-both existing
and new-for copying and distribution to each student.
2. South Oval Site
Model
This team will be responsible for construction of a site model (1"=30')
of the South Oval to incorporate both existing and projected buildings (if information
on the new Journalism Building and Parking garage is available). Boundaries to
be determined.
3. Existing Building Documentation This team must prepare
accurate CAD drawings of Gould Hall including a site plan, elevations and sections.
A floor plan is available (students of Professor Richard Ryan will assist with
surveying). In addition the team will be responsible for a site and context analysis.
4. Analysis of Precedents This team will select recent campus buildings by
distinguished architects for analysis. Each student on this team must prepare
a 20"x30" graphic illustration.
Phase One Review: Review of the phase
One (Data Collection) on Friday 09/8/00 @ 1:30pm in the Gallery. Walking Tour
OU Campus: There will be a walking tour of OU campus on Monday 09/11/00 @ 1:30pm.
Phase Two: Conceptual Design (30%) Each individual will prepare an architectural
concept for of the project. The following are required for this phase:
1.
Mass model of the of proposed building (1"=30') which to be examined against the
site model.
2. Drawings to show site access, building access (vehicular,
pedestrian, and service).
3. Vertical and horizontal access
4.
Block drawings (combining together Gould Hall and the proposed building) representing
floor plans, sections elevations.
5. New space planning for Gould Hall
in order to meet the requirements of the comprehensive program. 6. Sketches to
show a unified façade to integrate the exterior image of Gould Hall and the proposed
building.
Phase Two Review: This phase will be reviewed in two different
stages. " Preliminary: Monday 09/25/00 and Wednesday 09/27/00 @ 1:30pm in the
Gallery with Betsy Dougherty, FAIA, Goff Chair. " Final: Monday 10/09/00 and Wednesday
10/11/00 @ 1:30pm in the Gallery with Betsy Dougherty, FAIA, Goff Chair.
Phase
Three: Schematic Design (50%) The following are required for this review:
1.
Model of the Building which include identifiable architectural elements at the
site model scale (1"=30'). 2. Model of the proposed building and its relationship
to the renovated Gould Hall (1/8"=1'-0").
3. For additional requirements,
see "Schematic Design" in The Architect's handbook of Professional Practice (Student
Edition), "Design Phases", Section 3.63, pp.631-651.
Phase Three Review:
This phase will be reviewed in two different stages. " Preliminary: Review of
the Complete schematic designs on Wednesday 11/08/00 and Friday 11/10/00 @ 1:30pm
in the Gallery. "
Final: Review of complete, revised schematic designs
on Wednesday 12/06/00 and Friday 12/08/00 @ 1:30pm in the Gallery.
Gould
Hall
The
University of Oklahoma

Gould
Studio
Arch5595+Architectural/Urban
Design+Fall 2000
College
of Architecture, The University of Oklahoma
Dr.
Khosrow Bozorgi, Studio Professor
kbozorgi@ou.ed